Avondale – 2022 Street Preventive Maintenance
STREET | DISTANCE | TREATMENT | START DATE | END DATE |
---|---|---|---|---|
Beldare Avenue | West St to Vine St | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
9/20/2022 10/6/2022 | 9/22/2022 10/8/2022 |
Bogart Avenue | Glenwood Ave to South End | Crack Seal Micro-Surfacing |
9/9/2022 10/5/2022 | 9/12/2022 10/7/2022 |
Cleveland Avenue | Reading Rd to East End | Crack Seal Micro-Surfacing |
9/10/2022 10/6/2022 | 9/13/2022 10/8/2022 |
Cleveland Court | Cleveland Ave to South End | Crack Seal Micro-Surfacing |
9/9/2022 10/5/2022 | 9/12/2022 10/7/2022 |
Fredonia Avenue | Pavement Change North of Whittier to Ridgeway Ave | Crack Seal Micro-Surfacing |
9/9/2022 10/5/2022 | 9/12/2022 10/7/2022 |
Hartford Place | Blair Ave to Cleveland Ave | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
9/20/2022 10/5/2022 | 9/22/2022 10/7/202 |
Lexington Avenue | Victory Pkwy to Reading Rd | Crack Seal Micro-Surfacing |
9/10/2022 10/6/2022 | 9/13/2022 10/8/2022 |
Magill Avenue | Hutchins Ave to Lexington Ave | Crack Seal Micro-Surfacing |
9/9/2022 10/5/2022 | 9/12/2022 10/7/2022 |
Perkins Avenue | Ridgeway Ave to Blair Ave | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
9/20/2022 10/5/2022 | 9/22/2022 10/7/2022 |
Tower Street | Vine St to Beldare Ave | Crack Seal Micro-Surfacing |
9/9/2022 10/5/2022 | 9/12/2022 10/7/2022 |
Wehrman Avenue | Whittier St to South End | Crack Seal Micro-Surfacing |
9/10/2022 10/6/2022 | 9/13/2022 10/8/2022 |
Whittier Street | Reading Rd to Wehrman Ave | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
9/20/2022 10/6/2022 | 9/22/2022 10/8/2022 |
Windham Avenue | Rockdale Ave to Reading Rd | Crack Seal Micro-Surfacing |
9/9/2022 10/5/2022 | 9/12/2022 10/7/2022 |
*Dates are subject to change due to weather and field conditions.
**Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.