Camp Washington – 2018 Street Preventive Maintenance

STREET DISTANCE TREATMENT START DATE END DATE
Bates Avenue Colerain Ave to East End Micro-Surfacing 8/8/2018 8/10/2018
Bates Alley Colerain Ave to Henshaw Ave Micro-Surfacing 8/8/2018 8/10/2018
Henshaw Avenue Bates Ave to Bates Alley Micro-Surfacing 8/8/2018 8/10/2018

*Dates are subject to change due to weather and field conditions.