Clifton – 2019 Street Preventive Maintenance

STREET DISTANCE TREATMENT START DATE END DATE
Cloister Drive Ruther Ave to East End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/12/2019
9/23/2019
9/16/2019
9/25/2019
Manor Hill Drive Ludlow Ave to North End Micro-Surfacing 9/21/2019 9/24/2019
Marmet Avenue Cloister Dr to North End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/12/2019
9/23/2019
9/16/2019
9/25/2019
Mcalpin Avenue Clifton Ave to Middleton Ave Micro-Surfacing 9/21/2019 9/24/2019
Oxford Terrace Hosea Ave to Brookline Ave Micro-Surfacing 9/23/2019 9/25/2019
Warren Avenue Clifton Ave to West End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/12/2019
9/21/2019
9/16/2019
9/24/2019

*Dates are subject to change due to weather and field conditions.