STREET DISTANCE TREATMENT START DATE END DATE
Algona Place Dauner Ave to Blair Ave Micro-Surfacing 8/29/2018 8/31/2018
Burke Avenue Malory Ct to Hewitt Ave Micro-Surfacing 8/31/2018 9/5/2018
Gilpin Avenue Woodburn Ave to Victory Pkwy Micro-Surfacing 8/29/2018 8/31/2018
Hewitt Avenue Hewitt Crescent St to Montgomery Rd Micro-Surfacing 8/30/2018 8/31/2018
Hines Alley Evanston Ave to Wold Ave Micro-Surfacing 8/29/2018 8/31/2018
Malory Court Evanston Ave to Wold Ave Micro-Surfacing 8/30/2018 8/31/2018
Neilson Place Woodburn Ave to East End Micro-Surfacing 8/31/2018 9/5/2018
St. Leger Place Woodburn Ave to West End Micro-Surfacing 8/29/2018 8/31/2018
Wabash Avenue Hewitt Ave to Duck Creek Rd Micro-Surfacing 8/29/2018 8/31/2018

*Dates are subject to change due to weather and field conditions.