Mt. Airy – 2018 Street Preventive Maintenance

STREET DISTANCE TREATMENT START DATE END DATE
Allaire Avenue Colerain Ave to Corp Line/Vogel Rd Micro-Surfacing 8/10/2018 8/13/2018
Cindy Lane North Bend Rd to North End Micro-Surfacing 8/10/2018 8/13/2018
Fairhill Drive Kirby Ave to Vogel Rd Micro-Surfacing 8/10/2018 8/13/2018
Flanigan Court Monfort Hills Ave to East End Micro-Surfacing 8/13/2018 8/15/2018
Fox Road North Bend Rd to Mt. Airy Ave Micro-Surfacing 8/13/2018 8/15/2018
Gracewood Avenue Fox Rd to Corp Line/Vogel Rd Micro-Surfacing 8/10/2018 8/13/2018
Hearthstead Lane Kiplingwood Dr to East End Micro-Surfacing 8/10/2018 8/13/2018
Intern Court Willowcove Dr to West End Micro-Surfacing 8/10/2018 8/13/2018
Kiplingwood Drive Kipling Ave to South End Micro-Surfacing 8/10/2018 8/13/2018
Kirby Avenue Fairhill Dr to Ruddy Ct Micro-Surfacing 8/13/2018 8/15/2018
Little Flower Avenue Kirby Ave to North End Micro-Surfacing 8/13/2018 8/15/2018
Mt. Airy Avenue Colerain Ave to Corp Line Micro-Surfacing 8/10/2018 8/13/2018
Raeburn Terrace Raeburn Dr to Pavement Change Micro-Surfacing 8/8/2018 8/10/2018
Ruddy Court South End to North End Micro-Surfacing 8/10/2018 8/13/2018
South Raeburn Drive Raeburn Dr to South End Micro-Surfacing 8/8/2018 8/10/2018
Timbercroft Court Kiplingwood Dr to East End Micro-Surfacing 8/10/2018 8/13/2018
Wielert Avenue South End to North End Micro-Surfacing 8/13/2018 8/15/2018
Willowcove Drive Kipling Ave to South End Micro-Surfacing 8/10/2018 8/13/2018

*Dates are subject to change due to weather and field conditions.