Mt. Washington – 2019 Street Preventive Maintenance

STREET DISTANCE TREATMENT START DATE END DATE
Autumnhill Court Spindlewick Ln to North End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/13/2019
10/1/2019
9/17/2019
10/3/2019
Berkshire Club Drive Corp Line to Corp Line Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/13/2019
10/1/2019
9/17/2019
10/3/2019
Old Timber Place Spindlewick Ln to East End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/13/2019
10/2/2019
9/17/2019
10/4/2019
Salem Road Wayside Ave to Canoe Ct Micro-Surfacing 10/1/2019 10/3/2019
Spindlewick Lane Trailwood Dr to Berkshire Club Dr Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/13/2019
10/2/2019
9/17/2019
10/4/2019
Trailwood Drive Spindlewick Ln to Spindlewick Ln Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/13/2019
10/1/2019
9/17/2019
10/3/2019

*Dates are subject to change due to weather and field conditions.