Walnut Hills – 2018 Street Preventive Maintenance

STREET DISTANCE TREATMENT START DATE END DATE
Alpine Place St. Paul Dr to St. James Ave Micro-Surfacing 8/29/2018 8/31/2018
Churchhill Avenue Mentor St to West End Micro-Surfacing 8/29/2018 8/31/2018
Francisco Street St. James Ave to Fulton Ave Micro-Surfacing 8/30/2018 8/31/2018
Fulton Avenue Windsor Ave to Park Entrance Micro-Surfacing 8/31/2018 9/5/2018
Mentor Avenue Martin Luther King Dr to North End Micro-Surfacing 8/30/2018 8/31/2018
Morris Street Gilbert Ave to Sinton Ave Micro-Surfacing 8/31/2018 9/5/2018
Park Avenue Windsor St to Francis Ln/Cypress St Micro-Surfacing 8/29/2018 8/31/2018
Park Avenue Francis Ln/Cypress St to William Howard Taft Rd Cape Seal – SAMI
Cape Seal – Micro-Surfacing
6/25/2018
8/29/2018
6/27/2018
8/31/2018
Park Avenue Chapel St to Foraker Ave Micro-Surfacing 8/29/2018 8/31/2018
Sinton Avenue Nassau St to Gilbert Ave Micro-Surfacing 8/31/2018 9/5/2018
St. James Avenue Eden Park Entrance to Curtis St Micro-Surfacing 8/31/2018 9/5/2018
St. Paul Drive Eden Park Drive to Alpine Pl/Eden Park Entrance Micro-Surfacing 8/31/2018 9/5/2018

*Dates are subject to change due to weather and field conditions.