Walnut Hills – 2018 Street Preventive Maintenance

STREET DISTANCE TREATMENT START DATE END DATE
Alpine Place
St. Paul Dr to St. James Ave
Micro-Surfacing
9/14/2018
9/17/2018
Churchhill Avenue
Mentor St to West End
Micro-Surfacing
9/14/2018
9/17/2018
Francisco Street
St. James Ave to Fulton Ave
Micro-Surfacing
9/15/2018
9/17/2018
Fulton Avenue
Windsor Ave to Park Entrance
Micro-Surfacing
9/17/2018
9/19/2018
Mentor Avenue
Martin Luther King Dr to North End
Micro-Surfacing
9/15/2018
9/17/2018
Morris Street
Gilbert Ave to Sinton Ave
Micro-Surfacing
9/17/2018
9/19/2018
Park Avenue
Windsor St to Francis Ln/Cypress St
Micro-Surfacing
9/14/2018
9/17/2018
Park Avenue
Francis Ln/Cypress St to William Howard Taft Rd
Cape Seal – SAMI
Cape Seal – Micro-Surfacing
6/25/2018
9/14/2018
6/27/2018
9/17/2018
Park Avenue
Chapel St to Foraker Ave
Micro-Surfacing
9/14/2018
9/17/2018
Sinton Avenue
Nassau St to Gilbert Ave
Micro-Surfacing
9/17/2018
9/19/2018
St. James Avenue
Eden Park Entrance to Curtis St
Micro-Surfacing
9/17/2018
9/19/2018
St. Paul Drive
Eden Park Drive to Alpine Pl/Eden Park Entrance
Micro-Surfacing
9/17/2018
9/19/2018

*Dates are subject to change due to weather and field conditions.