West Price Hill – 2019 Street Preventive Maintenance

STREET DISTANCE TREATMENT START DATE END DATE
Ashbrook Drive North End to Prosperity Pl Micro-Surfacing 9/26/2019 9/30/2019
Century Lane Kreis Ln to West End Micro-Surfacing 9/25/2019 9/27/2019
Dale Avenue Lockman Ave to Overlook Ave Micro-Surfacing 9/26/2019 9/30/2019
Fisk Avenue Westhaven Ave to South End Micro-Surfacing 9/25/2019 9/27/2019
Flower Avenue Trenton Ave to West End Micro-Surfacing 9/26/2019 9/30/2019
Francis Avenue Trenton Ave to West End Micro-Surfacing 9/26/2019 9/30/2019
Highridge Avenue Lockman Ave to Overlook Ave Micro-Surfacing 9/25/2019 9/27/2019
Kellywood Avenue Guerley Rd to North End Micro-Surfacing 9/25/2019 9/27/2019
Lockman Avenue Rapid Run Pk to Loretta Ave Micro-Surfacing 9/26/2019 9/30/2019
Loretta Avenue Overlook Ave to Omena Pl Micro-Surfacing 9/25/2019 9/27/2019
Loubell Lane Clanora Dr to Wilbud Dr Micro-Surfacing 9/25/2019 9/27/2019
Omena Place Glenway Ave to South End Micro-Surfacing 9/25/2019 9/27/2019
Pleasure Drive W. 8th St to South End Micro-Surfacing 9/26/2019 9/30/2019
Virgil Road Fehr Rd to Corp Line Micro-Surfacing 9/26/2019 9/30/2019

*Dates are subject to change due to weather and field conditions.