Mt. Lookout – 2024 Street Preventive Maintenance
STREET | DISTANCE | TREATMENT | START DATE | END DATE |
---|---|---|---|---|
Crest Circle | Glengyle Ave to South End | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
05/20 05/28 |
05/22 05/31 |
Crestwood Avenue | Principio Ave to Ault Woods Ln | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
05/20 05/28 |
05/22 05/31 |
Parkridge Place | Griest Ave to Observatory Ave | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
05/20 05/28 |
05/22 05/31 |
Suncrest Drive | Griest Ave to Herschel Ave | Cape Seal – SAMI Cape Seal – Micro-Surfacing |
05/20 05/28 |
05/22 05/31 |
*Dates are subject to change due to weather and field conditions.
**Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.